01
|
Mill & Overlay approximately 11 miles of US 45 from Cotton Gin Road to the Kemper County Line, known as Federal Aid Project No. NH-0002-03(094) / 108175301 in Lauderdale County.
|
|
|
1 2 Fax1 QandA
|
1 2
|
|
|
|
|
|
|
02
|
Mill & Overlay approximately 8 miles on US 49 From Seminary to the US 84 Bypass, known as Federal Aid Project Nos. STP-0008-02(116) / 107731301 & HSIP-0008-02(120) / 1077313011 in Covington County.
Project Completion: 9/30/2021
|
|
|
1 2 Fax1 QandA
|
1 2
|
|
|
|
|
|
|
03
|
Slide Repair on US 49 Northbound approximately 3 miles South of SR 16, known as Federal Aid Project No. NHPP-0008-04(071) / 108502301 in Yazoo County.
Project Completion: 6/27/2021
|
|
|
1 2 Fax1 QandA
|
1 2
|
|
|
|
|
|
|
04
|
Bridge Preservation on SR 35 over the Pearl River (Bridge No. 19.4), known as Federal Aid Project No. BR-0014-02(069) / 106787301 in Marion County.
|
|
|
1 2 3 Fax1 QandA
|
1 2 3
|
|
|
|
|
|
|
05
|
Mill & Overlay approximately 13 miles on SR 35 from Tallahatchie County Line to SR 6, known as Federal Aid Project No. NH-0017-01(015) / 108252301 in Panola County.
|
|
|
1 2 Fax1
|
1 2
|
|
|
|
|
|
|
06
|
Safety Improvements along SR 13 from Lumberton to the Marion County Line, known as Federal Aid Project No. HSIP-0023-01(088) / 108426301 in Lamar County.
|
|
|
1 2 Fax1
|
1 2
|
|
|
|
|
|
|
07
|
Mill & Overlay approximately 4 miles of SR 35 beginning at the Begin Maintenance Section in North Carrolton going North to the 4 Forks, known as Federal Aid Project No. STP-0041-02(024) / 108251301 in Carroll County.
|
|
|
1 2 Fax1
|
1 2
|
|
|
|
|
|
|
08
|
Mill & Overlay & Striping approximately 2 miles on I-69 from Concrete Section to Tennessee State Line, known as Federal Aid Project Nos. IM-0069-04(003) / 108582301 & IM-0069-04(004) / 108583301 in Desoto County.
|
|
|
1 2 3 Fax1 QandA
|
1 2 3
|
|
|
|
|
|
|
09
|
Bridge Repair on I-55 over Long Creek (Bridge Nos. 237.7A & 237.7B), known as Federal Aid Project No. NHPP-0055-04(110) / 108458301 in Panola County.
|
|
|
1 2 3 4 5 6 Fax1 Fax2 QandA
|
1 2 3 4 5 6
|
|
|
|
|
|
|
11
|
Mill & Overlay approximately 5 miles on US 80 From SR 13 to West of Kalem, known as Federal Aid Project No. STP-2904-00(017) / 107629301 in Scott County.
|
|
|
1 2 Fax1
|
1 2
|
|
|
|
|
|
|
12
|
Overlay approximately 10 miles on US 51 from US 84 to the Copiah County Line, known as Federal Aid Project No. NHPP-9515-00(006) / 107619301 in Lincoln County.
Project Completion: 12/20/2021
|
|
|
1 2 Fax1 QandA
|
1 2
|
|
|
|
|
|
|
14
|
Upgrade of Administration Building HVAC Control System & 3rd Floor Space Reallocation, known as State Project No. BWO-9021-25(010) / 503251301 in Hinds County.
Project Completion: 1/11/2022
|
|
|
1 2 3 Fax1 QandA
|
1 2 3
|
|
|
|
|
|
|