01
|
Scrub Seal and Overlay approximately 8 miles of SR 12 from Black Creek in Lexington to Ellington Road, known as Project No. SP-0018-02(061) / 109043301 in Holmes County.
Project Completion: 10/15/2026
|
|
|
|
|
|
|
|
|
|
Request to Bid
|
|
02
|
Level & Overlay approximately 8.4 miles on SR 18 from Smith County Line to east of Bay Springs (Antioch Church) & Widen, Level & Overlay approximately 1 miles of SR 531 from Smith County Line to SR 18, known as Project Nos. MP-6018-31(012) / 308887301 & MP-6528-31(001) / 308889301 in Jasper County.
Project Completion: 5/7/2027
|
|
|
|
|
|
|
|
|
|
Request to Bid
|
|
03
|
Seal & Overlay approximately 16 miles of MS 501 from SR 18 to the Scott County Line, known as Project No. SP-0333-00(014) / 109047301 in Smith County.
Project Completion: 5/21/2027
|
|
|
|
|
|
|
|
|
|
Request to Bid
|