MDOT Contracts Advertised for a February 26, 2019 letting.
Click Call # to Email a Question
CallDescriptionProposalEBSx FileAddendaEBSx AmendFuel PricesBid ListCadd FilesPlan IndexPermit DocBid Tabulations
01 Mill & Overlay approximately 4 miles of US 45 from the End of Divided Lanes to Monroe County Line, known as Federal Aid Project No. NH-0002-05(089) / 107675301 in Lowndes County.
1
1
02 Mill & Overlay approximately 8 miles of US 49 E from SR 32 W to US 49 W, Overlay approximately 0.5 miles of US 49 W from Sunflower County Line to Tallahatchie County Line, & Overlay approximately 2 miles of US 49 W from Coahoma County Line to Tutwiler, known as Federal Aid Project Nos. STP-0008-05(041) / 107698301 & STP-0072-04(028) / 107774301 & 107774302 in Tallahatchie & Coahoma Counties.
1
QandA
1
03 Overlay approximately 10 miles of US 82 from US 49 W to Leflore CL, known as Federal Aid Project No. NH-0011-01(069) / 107720301 in Sunflower County.
04 Scrub Seal & Overlay approximately 9 miles of US 82 from 0.27 miles E of SR 182 to the Webster County Line, known as Federal Aid Project No. NH-0011-02(091) / 107770301 in Montgomery County.
QandA
05 Scrub Seal & Thin Lift approximately 9 miles of SR 28 from SR 13 East to US 49, known as Federal Aid Project No. STP-0013-02(031) / 107804301 in Simpson County.
1
1
06 Mill & Overlay approximately 3 miles of US 84 from the Mississippi River Bridge to US 61, known as Federal Aid Project No. STP-0015-01(136) / 107728301 in Adams County.
1
2
QandA
1
2
07 Bridge Removal on SR 43, Bridge Nos. 185.2 & 184.7, known as Federal Aid Project No. STP-0037-04(060) / 107490301 in Madison County.
1
2
QandA
1
2
08 Mill & Overlay approximately 12 miles of SR 18 from the beginning of the 4-lane South of Raymond to I-20, known as Federal Aid Project No. STP-0039-02(053) / 107631301 in Hinds County.
1
QandA
1
09 Bridge Preservation on SR 6 between SR 776 & SR 371, Bridge Nos. 148.2 & 146.8, known as Federal Aid Project No. BR-0053-01(016) / 107857301 in Monroe County.
1
QandA
1
11 Bridge Preservation on I-55 from Batesville to Hernando, known as Federal Aid Project Nos. NHPP-9999-06(018) / 106720302, 106720303, & 106720304 in Desoto, Panola, & Tate Counties.
Project Completion: Contractor Determined
1
2
3
Fax1
QandA
1
2
3
12 Mill & Overlay approximately 9 miles of SR 4 from US 61 to SR 3, known as Federal Aid Project No. STP-0060-01(017) / 107772301 in Tunica County.
1
QandA
1
13 Pavement Restoration on SR 53 from S. of Cuevas Gravel Pit Road to I-59, known as Federal Aid Project No. HSIP-0064-01(035) / 107901301 in Pearl River County.
1
1
14 Mill & Overlay approximately 10 miles of US 278 from Panola County Line to 0.25 miles West of Coliseum Drive, known as Federal Aid Project No. NH-0070-04(027) / 107773301 in Lafayette County.
1
QandA
1
16 Placing Audible Edge Stripe and Signs on SR 363 from SR 178 South to the Lee County Line, known as Federal Aid Project No. HSIP-0862-00(020) / 107550301 in Itawamba County.
QandA
17 Overlay approximately 6 miles of US 11 from Millard North, known as Federal Aid Project No. STP-1125-00(004) / 107782301 in Pearl River County.
1
1
18 Overlay approximately 12 miles North of Clara SR 63 from Greene County Line, known as Federal Aid Project No. NH-1132-00(010) / 107790301 in Wayne County.
1
QandA
1
19 Bridge Painting on SR 182 at Trim Cane Creek (Bridge No. 143.7) and SR 30 at Big Brown Creek (Bridge No. 74.5), known as Federal Aid Project Nos. BR-1708-00(002) / 107816301 & BR-0044-02(038) / 107816302 in Oktibbeha and Prentiss Counties.
QandA
20 Mill & Overlay approximately 2 miles of US 80 from beginning of 3-lane to Eastgate Circle, known as Federal Aid Project No. STP-2904-00(016) / 107622301 in Scott County.
1
2
3
QandA
1
2
3
21 Bridge Preservation on US 80 over the Pearl River, Bridge No. 46.4, known as Federal Aid Project Nos. BR-7314-00(030) / 1075693010 & 1075693011 in Hinds & Rankin Counties.
1
2
3
QandA
1
2
3