GEOM Link 
Proj Begin Month AscendingNot filtered
District AscendingNot filtered
2 Mnth Not filtered
Proj No Ascending
Fed Proj No Not filtered
Parallel To Proj No Not filtered
County Not filtered
Route Not filtered
Scope Of Work Not filtered
Termini Not filtered
 
Open filter row popup menu
Open filter row popup menu
Open filter row popup menu
Open filter row popup menu
Open filter row popup menu
Open filter row popup menu
Open filter row popup menu
Open filter row popup menu
Open filter row popup menu
Open filter row popup menu
2025 / 10District 1 109673/301000STBG-0016-01(037) MonroeUS 278Bridge RepairUS 278 over Buttahatchie River (#21.6)
2025 / 10District 1 109730/301000STBG-9999-01(414) LowndesUS 82Bridge RepairOld West Point Road over US 82 (BR# 160.3)(MRP 309549)(replace damaged span)
2025 / 10District 1 109730/301100STBG-9999-01(414)109730/301000LowndesUS 82Bridge RepairOld West Point Road over US 82 (BR# 160.3)(Raise bridge and approaches)
2025 / 10District 1 110032/301000HRRR-2837-00(005) ItawambaMS 23SafetyMS 23 from School Loop Drive in Tremont to Alabama State Line - Install center audible stripe, replace curve and intersection warning signs, refresh striping, and install RPMs
2025 / 10District 1 110033/301000HRRR-0752-00(005) ChoctawMS 413SafetyMS 413 from MS 12 to West of McCool Road in French Camp - Install edge audible stripe, replace curve and intersection warning signs, refresh striping, and install RPMs
2025 / 10District 1 110033/302000HRRR-0752-00(005)110033/301000LowndesMS 50SafetyMS 50 from Lindy Drive to Alabama State Line - Install edge audible stripe, replace curve and intersection warning signs, refresh striping, and install RPMs
2025 / 10District 2 109695/301000STBG-7903-00(002) DeSoto Bridge RepairCraft Road & Miller Road over US 78 (#1.4 & 8.5)
2025 / 10District 2 109696/301000STBG-0914-00(041)109695/301000MarshallMS 309Bridge RepairSR 309 over I-22 (#16.0A & 16.0B)
2025 / 10District 2 109698/301000NHPP-0006-01(107)109695/301000DeSotoUS 78Bridge RepairUS 78 over SR 305 (#4.3A & 4.3B)
2025 / 10District 2 109699/301000NHPP-0006-01(108)109695/301000MarshallI 22Bridge RepairI-22 over Stonewall Rd (#13.3A & 13.3B)
2025 / 10District 2 110031/301000HRRR -1924-00(003) TateMS 4SafetyMS 4 from MS 3 to Matthew Drive in Senatobia - Audible Stripe for centerline, refreshed striping, and install RPMs treatment
2025 / 10District 3 106110/301000STBG-0400-00(046)  WarrenMS 465Bridge ReplacementSR 465 [Bridge # 15.7]
2025 / 10District 3 110035/301000HRRR-1515-00(014) HolmesMS 433SafetyMS 433 from the Yazoo County Line to Ebenezer-Coxburg Road in Benton - Audible Stripe
2025 / 10District 3 110035/302000HRRR-1515-00(014)110035/301000YazooMS 433SafetyMS 433 from Old Highway 16 to the Holmes County Line - Audible Stripe
2025 / 10District 5 104422/303199SP-7334-00(013) RankinMS 477Grade Drain Bridge Pave 4 LanesSR 477 FR US 80 TO SR 468 (non Fed part)
2025 / 10District 5 107643/302000BR-2904-00(018) RankinUS 80Bridge ReplacementUS 80 bridge replacement over KCS RR (#56.8 A & B)
2025 / 10District 5 109677/301000NHPP-0220-03(038) HindsI 220Bridge RepairI-220 over Lynch St (0.5A & 0.5B)
2025 / 10District 5 109678/301000NHPP-0055-02(283)109677/301000MadisonI 55Bridge RepairI-55N to I-220 W (#11.4)
2025 / 10District 5 109679/301000STBG-0674-00(004) NoxubeeMS 145Bridge RepairSR 145 over Noxubee River Relief (#131.1)
2025 / 10District 5 109971/301000IM-0020-01(292) HindsI 20Mill & OverlayI-20 from Clinton to MS 18
2025 / 10District 6 109463/301000NHPP-0080-01(021) ForrestUS 49Mill & OverlayUS 49 From US 11 to Begin Divided Section at I-59
2025 / 10District 7 109002/301000SP-0013-03(030) SmithMS 28OverlaySR 28 Fr Mize to Taylorsville
2025 / 10District 7 109002/301999SP-0013-03(030)109002/301000SmithMS 28OverlaySR 28 Fr Mize to Taylorsville
2025 / 10District 7 109667/301000NHPP-0014-02(096) WalthallUS 98Bridge RepairUS 98 Magees Creek and relief bridges (#99.0, 99.0B, 99.1, & 99.1B)
2025 / 10District 7 109668/301000NHPP-0009-01(157) AdamsUS 61Bridge RepairUS 61 over St. Catherine Creek (49.5A & 49.5B)
2025 / 11District 1 108922/301000NHPP-0079-02(019) MonroeUS 45AMill & OverlayUS 45A FROMM CHICKASAW COUNTY LINE TO LEE COUNTY LINE
2025 / 11District 1 110034/301000STBG-0040-03(028) TishomingoMS 25Bridge RepairMS 25 Over Sandy Creek (Bridge. #221.3)
2025 / 11District 2 109693/301000STBG-9422-00(002) Lafayette Bridge RepairS. Lamar Blvd over US 278 (#76.2)
2025 / 11District 2 109694/301000NHPP-0019-02(067)109693/301000LafayetteMS 7Bridge RepairSR 7 over MS Central RR (#128.4)
2025 / 11District 3 106110/302000STBG-0400-00(047)  IssaquenaMS 465Bridge ReplacementSR 465 [Bridge # 8.7]
2025 / 11District 3 106110/303000STBG-0400-00(048)106110/302000WarrenMS 465Bridge ReplacementSR 465 Bridge Replacement # 2.6
2025 / 11District 3 108856/301000STBG-0013-02(035) CopiahMS 28Bank StabilizationSR 28 over Copiah Creek (55)
2025 / 11District 3 109685/301000STBG-0072-02(033) YazooMS 3Bridge RepairSR 3 over Short Creek (#32.7)
2025 / 11District 3 109706/301000STBG-9999-03(404) Warren Bridge RepairMt. Alban Road and Brabston Road Road (7.2A, 7.2B, and 12.7)(off)
2025 / 11District 5 108281/301000NHPP-0056-01(105) RankinMS 25Bridge PreservationSR 25 over Plummer Slough (12.7)
2025 / 11District 5 108513/301000STP-0020-01(260) HindsI 20DrainageI-20 Ditch Repair near Springridge Road Interchange
2025 / 11District 5 109926/301000HSIP-0039-02(060) HindsMS 18SafetyMS 18 from Old Port Gibson Road to the Copiah County Line - installation of center line rumble strips
2025 / 11District 5 503251/302000BWO-9021-25(014) Hinds Building ImprovementsRenovation of Admin Building 2nd Floor
2025 / 11District 7 107851/301000BR-0331-00(013) SmithMS 481Bridge ReplacementSR 481 BTW SR 902 to SR 35 (2.1 and 2.3)
2025 / 11District 7 109363/301000HSIP-0015-02(131) CovingtonUS 84SafetyUS 84 at MS 184 and at MS 588 in Collins - RCUT
2026 / 01District 1 108650/301000NHPP-0077-01(007) PontotocUS 278Mill & OverlayUS 278 From Just West Of SR 338 To SR 15
2026 / 01District 1 109562/301000NHPP-9432-01(002) ItawambaMS 76Restricted Crossing U-Turn (RCUT)SR 76 at SR 23 - Restricted Crossing U-Turn
2026 / 01District 1 109672/301000STBG-0044-01(036) UnionMS 30Bridge RepairSR 30 over Tallahatchie River (#19.0)
2026 / 01District 1 110051/301000SP-0733-00(013) WebsterMS 403Thin LiftMS 403 from junction US 82 to end of state maintenance (Resurface Ultra Thin)
2026 / 01District 2 102383/302000BR-0051-02(023) TallahatchieMS 32Bridge ReplacementSR 32 between Webb & Charleston [Bridge # 45.6, 46.2 & 47.0] - applied for grant
2026 / 01District 2 106103/301000BR-2909-00(006) MarshallMS 178Bridge ReplacementSR 178 [Bridge #s 33.6, 34.1, 35.2, 35.4 & 35.6]
2026 / 01District 2 109064/301000STBG-7889-00(002) DeSotoUS 51RoundaboutUS 51 at Green T Road
2026 / 01District 2 109755/301000STP-0050-01(043) CalhounMS 9Mill & OverlaySR 9 from SR 9W to Pontotoc County Line
2026 / 01District 3 109020/301000STBG-0013-02(036) CopiahMS 28OverlayMS 28 From Stuarts Body Shop To Simpson County Line
2026 / 01District 3 109686/301000STBG-0013-02(038) CopiahMS 28Bridge RepairSR 28 over CNIC RR (#47.6)
2026 / 01District 3 109688/301000NHPP-0055-01(133)109686/301000CopiahI 55Bridge RepairI-55 over Clear Creek Rd (#65.0A & 65.0B)
2026 / 01District 3 109687/301000NHPP-0009-03(073) WashingtonUS 61Bridge RepairUS 61 over Deer Creek (#179.1)
2026 / 01District 3 109689/301000NHPP-0072-04(034)109687/301000SunflowerUS 49WBridge RepairUS 49W over Lake Dawson (#244.7A & 244.7B)
2026 / 01District 5 109032/301000STBG-9999-05(405) MadisonMS 463Traffic SignalHWY 463 at Stribling Road
2026 / 01District 5 109082/301000STBG-9585-00(001) NeshobaMS 486Bridge ReplacementSR 486 Bridge Replacement (#1.0)
2026 / 01District 5 109783/301000STP-0456-00(006) LauderdaleMS 854Mill & OverlaySR 854 From SR 39 to Naval Air Station
2026 / 01District 5 309962/301000MP-5487-40(016) LeakeMS 487Mill & OverlayMS 487 from east of Tuscolameta Big Canal to MS 35
2026 / 01District 6 108392/301000STP-0022-01(089) HarrisonMS 15Bridge ReplacementSR 15 over Cypress Branch (#15.7)
2026 / 01District 6 109879/301000NHPP-0010-01(185) HarrisonI 10WideningI-10 at MS 605 WB ramp - Widen and lengthen
2026 / 01District 7 108976/301000STBG-0014-01(077) PikeMS 24OverlayMS 24 From Amite County Line to I-55
2026 / 01District 7 109580/301000HSIP-0015-01(151) FranklinUS 84Restricted Crossing U-Turn (RCUT)US 84 at MS 33
2026 / 01District 7 109797/301000NHPP-0015-01(152) LincolnUS 84OverlayUS 84 From Concrete Section at Monticello Street NE to Lawrence CL
2026 / 01District 7 110060/301000SP-9999-07(402) Districtwide - D7 Raised Pavement MarkersDistrict Wide Raised Pavement Markers
2026 / 02District 2 109378/301000HSIP-0070-04(029) LafayetteUS 278Restricted Crossing U-Turn (RCUT)US 278 at CR 217/405
2026 / 02District 2 109983/301000SP-0035-01(009) MarshallMS 311Mill & OverlaySR 311 from Landfill Road to Liles Road
2026 / 02District 2 109984/301000SP-0035-01(010)109983/301000MarshallMS 311OverlaySR 311 from 0.1m S of Audie Todd to US72
2026 / 02District 3 109021/301000STBG-0054-01(060) CopiahMS 27Mill & OverlayMS 27 From 0.2 Mile South Of Old Highway 27 To 0.35 Mile North Of I-55 (widen)
2026 / 02District 5 108246/301000NH-0056-01(106) LeakeMS 25Mill & OverlaySR 25 From Renfroe To Attala CL
2026 / 02District 5 109005/301000SP-0002-03(097) NoxubeeUS 45Mill & OverlayUS 45 Fr S of Macon Bypass To Brooksville
2026 / 02District 5 109403/301000HSIP-0002-03(098)109005/301000NoxubeeUS 45Intersection ImprovementsUS 45 fr Misso Road to Magnolia Drive
2026 / 02District 6 109171/301000STBG-0010-01(180) JacksonI 10Building Construction - Welcome CenterI-10 Jackson County Welcome Center
2026 / 02District 7 109004/301000STBG-0199-00(011) MarionMS 44Thin LiftMS 44 Fr Gates Rd to Lamar CL (8.34 - 16.74)
2026 / 03District 1 109902/301000NHPP-0002-06(034) LeeUS 45Intersection Improvement - Mast ArmsUS 45 & US 278 Traffic Signal and Interchange Modifications - Northbound Ramp Traffic Signal and Ramp Widening at US 278
2026 / 03District 1 503862/301000BWO-1201-41(001) Lee Building ConstructionLee Co Maint & Float Crew Bldg
2026 / 03District 1 503862/302000LWO-1033-41(006) Lee Lot ImprovementLee Co Maint & Float Crew Bldg Site Improvements
2026 / 03District 1 503862/303000BWO-1202-41(001) Lee Building ConstructionConstruction of Lee Co Maint Equipment Shed
2026 / 03District 1 503862/304000BWO-1050-41(003) Lee Building ImprovementsRenovation of Material Storage Building
2026 / 03District 2 100222/303200SP-0055-04(122) DeSotoMS 302ITS - Intelligent Transportation SystemsI-55 FROM CHURCH ROAD TO SR 302 (ITS along 302) (SR 302 from East of Sutton Drive to west of Malco Drive)
2026 / 03District 2 109440/301000NHPP-0009-05(038) TunicaUS 61Seal & OverlayUS 61 From Tunica Agriculture Center to Desoto County Line
2026 / 03District 2 110057/301000SP-0051-02(030) YalobushaMS 330SealMS 330 from east of Front Street to Calhoun County Line - Scrub Seal
2026 / 03District 2 110058/301000SP-0051-03(011)110057/301000CalhounMS 330SealMS 330 From Yalobusha CL to MS 32 - Scrub Seal
2026 / 03District 5 105530/301000NH-0008-03(050) MadisonUS 49Pavement RestorationUS 49 FROM HINDS COUNTY LINE TO THE YAZOO COUNTY LINE
2026 / 03District 5 109486/301000NHPP-0020-01(291) HindsI 20Design BuildI-20 from just West of Wiggins Road to the Rankin County Line, I-55 From McDowell Road to I-20, I-55 from Rankin County Line to 94.3 A & B, I-220 from I-20 to the south of the Lynch Street Bridges & US 51 from I-55 to EOSM
2026 / 03District 5 109486/302000NHPP-0020-01(291) RankinI 20Design BuildI-20 from the Rankin County Line to Pearson Road & I-55 from I-20 to the Rankin CL
2026 / 03District 6 109465/301000STP-0022-01(094) JonesMS 15Micro SurfaceSR 15 Fr Ovett-Scarbrough Rd to S of Tuckers Crossing (11.4 Miles)
2026 / 03District 6 109466/301000SP-0022-01(094)109465/301000JonesMS 536Micro SurfaceSR 536 from SR 15 to EOSM (1.8 Mi)
2026 / 03District 6 109669/301000NHPP-0014-02(097) LamarUS 98Bridge RepairUS 98 over I-59 (#149.1)
2026 / 03District 6 109792/301000NH-0014-03(080) PerryUS 98Seal & OverlayUS 98 From 1.05 Mile East of SR 29 to Greene County Line
2026 / 03District 7 106972/301000STP-2175-00(014) PikeUS 51Bridge ReplacementUS 51 over Unnamed Streams [Bridge #s 11.7 & 12.1]
2026 / 03District 7 106972/302000STP-2175-00(016)106972/301000PikeUS 51Bridge ReplacementUS 51 two Northern Bridge Replacements between Magnolia and Fernwood (13.3 and 13.4)
2026 / 03District 7 108980/301000STBG-0015-01(149) FranklinUS 84Thin LiftUS 84 from Bude to the Homochitto River Bridge
2026 / 03District 7 109006/301000STBG-0054-01(059) LawrenceMS 27Thin LiftMS 27 from US 84 to the Copiah County Line
2026 / 04District 1 307877/301000MP-1371-29(006) ItawambaMS 371Mill & OverlaySR 371 from Mantachie Corp. limit to Prentiss County Line
2026 / 04District 1 308838/301000MP-1145-59(004) PrentissMS 145Mill & OverlaySR 145 From Begin 4-Ln Section Near Cedar Dr to SR 4
2026 / 04District 2 108287/302000STP-0018-02(057)108287/301000AttalaMS 12Bank StabilizationSR 12 over Big Black River (83.4)
2026 / 04District 2 109438/301000NHPP-0060-03(026) Marshall Mill & OverlaySR 4/SR 7 From Lafayette County Line to I-22
2026 / 04District 2 110039/301000STBG-0035-01(011) MarshallMS 311Bridge RepairMS 311 over Little Coldwater River (Bridge # 11.8)
2026 / 04District 2 110040/301000NHPP-0055-04(123) DeSotoI 55Bridge RepairI-55 over Star Landing Road (Bridge #s 285.9 A & 285.9 B)
2026 / 04District 2 110045/301000NHPP-0008-05(044) CoahomaUS 49Bridge RepairUS 49 over Big Sunflower River Tributary (Bridge # 305.6)
2026 / 04District 3 108186/301000STBG-0091-02(010) HumphreysMS 149Widen & OverlayMS 149 From 0.3 Miles South of SR 14 to US 49W
2026 / 04District 3 108287/301000STP-0018-02(057) HolmesMS 12Bank StabilizationSR 12 over Big Black River (83.4)
2026 / 04District 5 107569/303000STBG-7314-00(039) HindsUS 80Bridge PreservationUS 80 and I-20/55 over Pearl River Scour (3BR)(46.4, 46.4A and 46.4B)
2026 / 04District 5 107569/303100STBG-7314-00(039)107569/303000Rankin Bridge PreservationUS 80 and I-20/55 over Pearl River Scour (3BR)(46.4, 46.4A and 46.4B)
2026 / 04District 5 109131/301000HSIP-7314-00(040) HindsUS 80Median BarrierUS 80 from Clinton-Raymond Road to Shaw Road
2026 / 04District 5 110008/301000SP-1441-00(008) HindsMS 467Micro SurfaceMS 467 from beginning of maintenance to South of Edwards
2026 / 04District 5 110009/301000SP-0024-01(036) HindsMS 22Micro SurfaceMS 22 From I-20 to Madison County Line
2026 / 04District 5 308848/301000MP-5000-00(193) Districtwide - D5 Raised Pavement MarkersD5 FY 2027 Districtwide Raised Pavement Markers
2026 / 04District 5 309963/301000MP-5482-50(007) NeshobaMS 482Micro SurfaceMS 482 from SR 16 to SR 491
2026 / 04District 7 307907/301000MP-7550-43(011) LincolnMS 550OverlayMS 550 From Jefferson County Line to East of Bouie Mill Road Northwest
2026 / 05District 1 109707/301000STBG-2708-00(002) LowndesMS 373Bridge RemovalSR 373 (#9.9)
2026 / 05District 1 109707/302000STBG-2708-00(002)109707/301000MonroeMS 373Bridge RemovalSR 373 (#9.9 & #10.3)
2026 / 05District 1 310038/301000MP-1172-71(002) TishomingoMS 172OverlayMS 172 from junction of US 72 to junction of US 72 (Scrub Seal & Overlay)
2026 / 05District 2 309966/301000MP-2178-05(002) BentonMS 178Mill & OverlayMS 178 from Marshall County Line to Union County
2026 / 05District 3 107036/301000BR-0013-00(052) JeffersonMS 28Bridge ReplacementSR 28 bridge removal over Abandoned RR (Bridge #2.4), bridge replacement over Boles Creek (Bridge #2.7), and box replacement
2026 / 05District 3 108865/301000STBG-0091-01(009) YazooMS 149Bridge RepairSR 16/SR 149 over SR 3 & Yazoo River (203.3)
2026 / 05District 5 102372/302000BR-0551-00(115) LeakeMS 427Bridge ReplacementSR 427 BTW SR 488 AND SR 16 (4.4)
2026 / 05District 5 109833/301000NHPP-7281-00(007) HindsI 55Bridge RepairI- 55 N ramp to Woodrow Wilson Drive (#97.0)
2026 / 05District 6 308887/301000MP-6018-31(012) JasperMS 18OverlaySR 18 from Smith County Line East 2.99 Miles to eastern corporate limits of Bay Springs
2026 / 05District 6 308889/301000MP-6528-31(001)308887/301000JasperMS 531Widen & OverlaySR 531 From Smith County Line to SR 18
2026 / 05District 6 309590/301000MP-6026-55(018) Pearl RiverMS 26Widen & OverlaySR 26 From East End of Pearl River Bridge to East Bridge Abutment of White Sands Bridge
2026 / 05District 7 106971/301000BR-0013-02(029)100881/301000SimpsonMS 28Bridge ReplacementSR 28 over Tanyard Creek [Bridge # 77.6]
2026 / 05District 7 100881/301000STBG-0013-02(034)106971/301000SimpsonMS 28Bridge ReplacementSR 28 between Copiah CL & Pinola [Bridge #s 72.7 & 73.6]
2026 / 05District 7 308852/301000MP-7033-03(003) AmiteMS 33OverlaySR 33 Truck Lane Section
2026 / 06District 1 109513/301000STBG-9999-01(409) Districtwide - D1 Bridge RepairD1 - Pile/Encasement Repair Project (24 Bridges)
2026 / 06District 1 109518/301000HSIP-0011-03(090) OktibbehaUS 82Restricted Crossing U-Turn (RCUT)US 82 at Sturgis-Maben Road
2026 / 06District 1 110038/301000STBG-0007-01(107) TishomingoUS 72Bridge RepairUS 72 over MS 25 (Bridge #s 84.9 A & 84.9 B) & MS 4 over Tenn-Tom Waterway (Bridge # 158.5)
2026 / 06District 1 309572/301000MP-1000-00(169) Districtwide - D1 Raised Pavement MarkersD1 Various Routes Raised Pavement Markers FY 27
2026 / 06District 2 109254/301000IM-0055-03(100) YalobushaI 55OGFC LiftI-55 from 0.4 mile north of MS 330 to the Panola County Line
2026 / 06District 2 109255/301000IM-0055-04(121)109254/301000PanolaI 55OGFC LiftI-55 Yalobusha County Line to 0.5 mile south of MS 6
2026 / 06District 2 109513/302000STBG-9999-02(398) Districtwide - D2 Bridge RepairD2 - Pile/Encasement Repair Project (13 Bridges)
2026 / 06District 2 308835/301000MP-2004-05(001) BentonMS 4Thin LiftSR 4 From SR 5 to Tippah County Line
2026 / 06District 3 109513/303000STBG-9999-03(394) Districtwide - D3 Bridge RepairD3 - Pile/Encasement Repair Project (7 Bridges)
2026 / 06District 6 109338/301000HSIP-0063-02(027) ForrestMS 42SafetyMS 42 from I-59 to Sunrise Road - Corridor Safety Improvements
2026 / 06District 6 109464/301000STP-0063-02(028)109338/301000ForrestMS 42OverlaySR 42 from west of I-59 to End of Divided Median
2026 / 06District 6 309953/301000MP-6000-00(309) Districtwide - D6 Raised Pavement MarkersRaised Pavement Markers Districtwide D6
2026 / 06District 7 109513/307000STBG-9999-07(397) Districtwide - D7 Bridge RepairD7 - Pile/Encasement Repair Project (32 Bridges)
2026 / 07District 1 107849/301000BR-0040-03(020) TishomingoMS 25Bridge ReplacementSR 25 BTW SR 4 and CR 23 (189.3)
2026 / 07District 1 108911/301000SP-0042-01(012) WinstonMS 397Mill & OverlaySR 397 From Kemper County Line To Robertson Road
2026 / 07District 1 109758/301000SP-0071-05(017) PrentissMS 4Mill & OverlaySR 4 From East of Church Street to West of Junction SR 371 At Hobo Station
2026 / 07District 1 109974/301000SP-0926-00(030) LeeMS 348Mill & OverlayMS 348 from Union Co. to Just West of US 45
2026 / 07District 2 108967/301000SP-7904-00(002) DeSotoMS 178Mill & OverlaySR 178 from East End of Olive Branch to Marshall County Line
2026 / 07District 2 108967/302000SP-7904-00(002)108967/301000MarshallMS 178Mill & OverlaySR 178 from Desoto County Line to West Holly Springs City Limits
2026 / 07District 2 110041/301000STBG-0642-00(028) AttalaMS 19Bridge RepairMS 19 over Big Black River (Bridge #114.9)
2026 / 07District 3 109043/301000SP-0018-02(061) HolmesMS 12OverlaySR 12 from Black Creek Bridge in Lexington to Ellington Rd. just west of I-55 (Scrub seal)
2026 / 07District 3 109044/301000SP-0013-01(017) CopiahMS 28OverlaySR 28 from Jefferson County Line to 1 mile east of Sylvarena Rd.
2026 / 07District 3 109171/302000STBG-0020-01-(271) WarrenI 20Building Construction - Welcome CenterI-20 Commissioner Dick Hall Hospitality Station
2026 / 07District 3 109230/301000SP-0037-01(071) YazooMS 149Mill & OverlayMS16/MS 149 from MS 3 to US 49
2026 / 07District 3 110042/301000STBG-0011-01(077) Washington Bridge RepairUS 82 over Bogue Phalia (Bridge # 22.1 B) & MS 438 over Bogue Phalia (Bridge # 11.1)
2026 / 07District 5 108781/305000STBG-9999-05(398) HindsI 220Bridge Preventive MaintenanceI-220 Bridge Preventative Maintenance (Bridge #s 1.2A, 1.2B, 7.7A, and 7.7B)
2026 / 07District 7 109047/301000SP-0333-00(014) SmithMS 501OverlayMS 501 from SR 18 to the Scott County Line
2026 / 07District 7 109967/301000SP-0196-00(033) LawrenceMS 587OverlayMS 587 From the Marion County Line to the Northern Ervin-Reid Circle Drive
2026 / 07District 7 110044/301000NHPP-0055-01(153) LincolnI 55Bridge RepairI-55 over CNIC RR (Bridge #s 40.3 A & 40.3 B)
2026 / 08District 1 109074/301000STBG-0053-01(017) LeeMS 145Bridge ReplacementSR 145 Bridge Replacement (#210.8)
2026 / 08District 1 110037/301000NHPP-0002-08(027) AlcornUS 45Bridge RepairUS 45 Over Norfolk Southern RR (Bridge #s 275.6A & 275.6B)
2026 / 08District 1 110052/301000SP-0998-00(009) TippahMS 354Thin LiftMS 354 from Junction of MS 15 to end of state maintenance (Resurface Ultra Thin)
2026 / 08District 2 309967/301000MP-2035-08(008) CarrollMS 35Mill & OverlayMS 35 from 200' S. of Co. Rd. 111 to Grenada County Line
2026 / 08District 3 108822/301000NHPP-0011-01(074) WashingtonUS 82Bridge PreservationUS 82 over MS River Bridge
2026 / 08District 3 109078/301000STBG-0502-00(009) SharkeyMS 434Bridge RepairSR 434 bridge repair on # 0.7 and a bridge rehabilitation on # 2.3
2026 / 08District 3 110047/301000SP-0011-01(078) WashingtonUS 82Ultra-thin OverlayUS 82 from the Greenville Bypass to 0.5 mile east of US 61
2026 / 08District 3 310032/301000MP-3550-32(001) JeffersonMS 550Ultra-thin OverlayMS 550 from SR 28 to Lincoln County Line
2026 / 08District 5 110043/301000NHPP-0055-02(287) MadisonI 55Bridge RepairI-55 over Church Road (Bridge #s 112.3 A & 112.3 B)
2026 / 08District 6 109083/301000STBG-2902-00(016) ClarkeUS 11Bridge ReplacementUS 11 Bridge Replacements (#145.2 & 143.3)
2026 / 09District 2 110064/301000IM-0055-04(124) DeSotoI 55OGFC LiftI-55 from Tate County Line north for 2.2 miles
2026 / 09District 2 110065/301000IM-0055-04(125)110064/301000TateI 55OGFC LiftI-55 from Panola County Line north approximately 5.18 miles and I-55 approximately 4.492 miles south of Desoto County Line to the Desoto County Line
2026 / 09District 2 110066/301000IM-0055-04(126)110064/301000TateI 55Fog SealI-55 from approximately 0.6 miles north of MS 4 to just south of Rifle Range Rd
2026 / 09District 5 110067/301000IM-0055-02(291) MadisonI 55OGFC LiftI-55 from Church Rd to Heindl Road
2026 / 09District 5 110068/301000IM-0055-02(292)110067/301000MadisonI 55Fog SealI-55 from Heindl Road to Yazoo County Line
2026 / 09District 5 110069/301000IM-0020-01(294) RankinI 20OGFC LiftI-20 from MS 18 to US 80 (East Brandon)
2026 / 09District 6 109087/301000STBG-0023-01(097) Pearl RiverMS 13Bridge ReplacementSR 13 Bridge Replacement (#10.8)
2026 / 09District 6 109087/302000STBG-0023-01(097)109087/301000Forrest Bridge ReplacementSR 13 Bridge Replacement (#10.8)
2026 / 09District 6 109467/301000SP-0231-00(090) JacksonMS 613Widen & OverlaySR 613 From SR 614 to George CL
2026 / 09District 6 308310/302000MP-6613-20(007)109467/301000GeorgeMS 613Widen & OverlaySR 613 from Jackson County Line North 6.41 Mile to Fire Department Road
2026 / 09District 6 110062/301000IM-0010-01(187) HarrisonI 10OGFC LiftI-10 from approximately 0.9 miles west of D'Iberville Boulevard overpass to the Jackson County Line
2026 / 09District 6 110063/301000IM-0010-01(188)110062/301000HarrisonI 10OGFC LiftI-10 from just east of Shorecrest Road to approximately 0.9 mile west of D'Iberville Boulevard overpass
2026 / 09District 6 110070/301000IM-0059-02(123) JasperI 59OGFC LiftI-59 from 0.8 mile north of CR 39 to the Clarke County Line
2026 / 09District 7 109492/301000NHPP-0015-01(150) FranklinUS 84Slide ImprovementUS 84 from west of Fire Tower Rd to east of Providence Road/Clear Spring Road
2026 / 09District 7 110061/301000IM-0055-01(154) PikeI 55OGFC LiftI-55 from Mississippi State Line to MS 568