01
|
Overlay approximately 6.5 miles on US 61 from Rolling Fork to 0.75 miles north of SR 14, Mill & Overlay approximately 0.3 miles on SR 824 in Anguilla, & Overlay approximately 0.25 miles of the State Maintained Access Road near the BOP, known as Federal Aid Project No. NH-0009-02(084) / 108210301 in Sharkey County.
|
|
|
1 2 QandA
|
1 2
|
|
|
|
|
|
|
02
|
Mill & Overlay approximately 11 miles on I-10 from just west of the Diamondhead Interchange in Hancock County to Wolfe Creek Bridge (Bridge Nos. 28.7 A & B), known as Federal Aid Project Nos. IM-0010-01(170) / 108585301 & 302 in Hancock & Harrison Counties.
|
|
|
1
|
1
|
|
|
|
|
|
|
03
|
Overlay approximately 11 miles on SR 35 from the north end of Bridge No. 248.1 to the Panola County Line, known as Federal Aid Project No. STP-0017-01(014) / 108263301 in Tallahatchie County.
|
|
|
1 QandA
|
1
|
|
|
|
|
|
|
04
|
Mill & Overlay approximately 22 miles on I-55 from 0.5 miles north of SR 17 to the Carroll County Line, known as Federal Aid Project No. IM-0055-02(257) / 108091301 in Holmes County.
|
|
|
1 2 3 4 QandA
|
1 2 3 4
|
|
|
|
|
|
|
05
|
Mill & Overlay approximately 8.4 miles on SR 25 from the Attala County Line to 1.3 miles north of Platsburg Road & approximately 2.2 miles on SR 19 from the Neshoba County Line to the Attala County Line, known as Federal Aid Project Nos. NH-0056-01(103) / 108218301 & 302 in Winston County.
|
|
|
1 QandA
|
1
|
|
|
|
|
|
|
07
|
Thin Lift Overlay approximately 8 miles on SR 613 from East Fire Dept. Rd. to Evanston Rd, known as Federal Aid Project No. STP-0231-00(088) / 108271301 in George County.
|
|
|
1 QandA
|
1
|
|
|
|
|
|
|
08
|
Mill & Overlay approximately 7 miles on SR 388 from Cliftonville to the Alabama State Line, known as Federal Aid Project No. STP-0658-00(011) / 108230301 in Noxubee County.
|
|
|
1
|
1
|
|
|
|
|
|
|
09
|
Overlay approximately 13 miles on US 51 from Tillatoba to the Panola County Line, known as Federal Aid Project No. STP-2901-00(037) / 108253301 in Yalobusha County.
|
|
|
1
|
1
|
|
|
|
|
|
|
10
|
Intersection Improvements on various routes throughout the District, known as Federal Aid Project No. HSIP-9999-03(017) / 107793301 in District 3.
Project Completion: 6/12/2023
|
|
|
1 QandA
|
1
|
|
|
|
|
|
|
11
|
Slide Repair on SR 145 approximately 2.3 miles north of the Clarke County Line, known as Federal Aid Project No. STP-9999-05(376) / 108000301 in Lauderdale County.
|
|
|
1
|
1
|
|
|
|
|
|
|
12
|
Mill & Overlay approximately 4 miles on SR 15 from the beginning of the 3-Lane section south of Ripley to the end of the 3-Lane section north of Ripley, known as State Project No. SP-0022-04(068) / 108893301 in Tippah County.
|
|
|
1
|
1
|
|
|
|
|
|
|
13
|
Mill & Overlay 2.5 miles on SR 13 from the Pearl River County Line to the End of Divided Section in Lumberton, known as State Project No. SP-0023-01(093) / 108926301 in Lamar County.
|
|
|
1 2 QandA
|
1 2
|
|
|
|
|
|
|
14
|
Thin Lift Overlay approximately 8.9 miles of SR 18 from SR 512 to SR 145, known as State Project No. SP-0065-02(011) / 108700301 in Clarke County.
|
|
|
1 QandA
|
1
|
|
|
|
|
|
|
15
|
Widen & Overlay approximately 11 miles on SR 29 from West ROW Limits of I-59 in Ellisville to SR 28 and Mill & Overlay the intersection of SR 15 and US 84 in Laurel & I-59 Ramps at Exit 96 A, Exit 96 B (Cook Ave.), and Exit 97 (US 84 East), known as State Project Nos. SP-0241-00(014) / 108924301 & SP-0059-02(115) / 108925301 in Jones County.
|
|
|
1 2 QandA
|
1 2
|
|
|
|
|
|
|
16
|
Mill & Overlay approximately 4 miles on SR 16 beginning just west of SR 397 to SR 39 in Dekalb and approximately 2 miles of SR 39 beginning at SR 16 and ending at the pavement change approximately 2 miles north of SR 16, known as State Project Nos. SP-0491-00(005) / 108998301 & SP-0074-02(015) / 108998302 in Kemper County.
|
|
|
1
|
1
|
|
|
|
|
|
|
17
|
Overlay approximately 8 miles on SR 3 from US 49 W to US 82 at Moorhead, known as State Project No. SP-0621-00(007) / 108930301 in Sunflower County.
|
|
|
1 QandA
|
1
|
|
|
|
|
|
|